How to use this estimate
Take widths and depths from your approved plan. Combine runs that have the same cross-section in section one; use the optional second section for a different width or depth. Count each corner and intersection once. Leave all three second-section dimensions at zero when unused. Add the section volumes before adding waste; the shared price is per unit of concrete volume, not per foot of footing.
Before you order
- Total non-overlapping runs; do not count corner intersections twice. Use the second section for a different width or depth.
- Confirm footing dimensions with the project designer before ordering. This tool estimates volume, not load-bearing adequacy.
The calculation
A worked example
A 40 ft run, 16 in wide and 8 in deep, uses 35.5556 ft³. Adding 10% gives 1.4486 yd³.
Main calculator scope: This calculator does not size foundations or verify soil bearing capacity, frost depth, reinforcement or building-code compliance. Use the optional supporting-materials section for separately quantified supplies.
Combining different footing sizes
A plan may call for one cross-section around the perimeter and another under an internal wall. Instead of averaging widths or depths, calculate each run separately. A 10 m run that is 0.4 m wide and 0.2 m deep contains 0.8 m³. A separate 6 m run that is 0.5 m wide and 0.25 m deep contains 0.75 m³. Together they need 1.55 m³ before allowance, or 1.705 m³ with 10% extra.
The optional second section handles that distinction. The shared material price applies to the combined order. If your sections require different concrete specifications or delivery schedules, obtain separate supplier quotations rather than treating them as one purchase.
A corner can be counted twice
Imagine two rectangular strips, each 4 m long, 0.4 m wide and 0.2 m deep, overlapping at one 0.4 × 0.4 m corner. Adding their full volumes gives 0.64 m³, but the shared corner occupies 0.032 m³. The combined volume is 0.608 m³. With the same cross-section, entering a non-overlapping total run of 7.6 m gives the same result.
That is a geometry example, not a universal corner deduction. A closed perimeter, a T-junction and strips of different widths need their own takeoff. Work from a sketch or approved drawing, mark the rectangles you counted, and identify overlap explicitly. Do not subtract at every corner automatically.
Keep the order separate from the structural design
- Use specified footing dimensions. This tool cannot select them from building size, soil type or climate.
- Include additional pads, steps and stem walls as separate volumes. The calculator does not infer hidden concrete from a plan.
- Measure formed or excavated dimensions where appropriate. An over-wide trench changes volume even when the drawing has not changed.
- Confirm concrete specification, access, pumping, order increments and delivery charges with the responsible contractor and supplier.
For bagged material, transfer the order volume to the bag calculator and set its waste to zero. If you instead transfer measured volume, apply the allowance there. This avoids adding the same contingency twice.
Footing preparation supplies
Estimate explicitly specified preparation materials without choosing a foundation design.
- Specified base aggregate: Enter the measured base footprint and specified finished depth. The base may extend beyond the visible surface. Enter a supplier-confirmed loose-volume multiplier; this tool does not design or infer compaction.
- Separation fabric / membrane: Only if specified for this installation. Enter usable installed coverage per roll after seams, overlaps, upturns and cuts. An area estimate is not a roll layout.
- Footing form boards: Enter only sides actually formed; excavated earth faces are not automatically formwork.
- Specified reinforcement chairs / spacers: Enter the quantity from the approved reinforcement takeoff. No bar sizing, spacing, lap, steel length or structural selection is calculated.
Use approved drawings for reinforcement, excavation, bearing conditions and dimensions. Optional membranes and base layers are not universal footing requirements.
Open Include installation supplies above to enter each selected product’s coverage or takeoff and round purchases to whole packages. Accessories use installed measurements, with a separate allowance for each line. Copy, print or download the calculated list as CSV; missing details and unpriced supplies remain explicit. Custom areas and run lists apply once to the entire selected scope.
Installation references, checked 2 November 2026: QUIKRETE slab preparation and finishing. Use the current instructions for the exact product; these references do not prescribe a complete assembly.
Common questions
Can I use it for isolated pads?
Calculate a single rectangular pad and multiply the quantity, or use the slab calculator for each size. Round the combined order only after adding the volumes.
References & method
QUIKRETE concrete mix product data. See how we check calculations. Reference links provide context; no supplier endorses this site.